High-Rise Floor Placement
Coordinate the concrete arrival rhythm with the floor working area. A separate placing boom needs an external supply pump and its own support assessment.
Look beyond a maximum distance: the concrete source, route, access and working area shape the delivery arrangement.


Coordinate the concrete arrival rhythm with the floor working area. A separate placing boom needs an external supply pump and its own support assessment.
Where concrete is mixed, its properties and expected arrival rhythm.
Horizontal sections, elevation, bends, pipework and pour zones.
Access, supports, clearances, utilities and cleaning provisions.